The October 2026 revised plan changes are a significant departure from the previous project plan called Sequoia:
The sequoia tree on site will no longer be retained and thus the development named has changed to Fernwood Apartments
The 11 townhouses have been removed from the development plans
Underground parking has been removed and reduced from 35 vehicle stalls to 28 surface level spots on permeable paver stones
The 1883 heritage house will still be retained, but now in its original location, not moved four metres south on the lot. With guidance from DLA Heritage Consultants, original materials and architectural features will be restored, replaced or rebuilt in accordance with the Conservation Plan.
Primex Investments October 2, 2026 letter explaining rationale for changes:
The revised plans have been informed by ongoing discussions with the City, site-specific considerations, and continued design development. Our primary focus remains providing purpose-built rental housing, restoring the existing heritage-designated MacLaughlin Residence, improving the public realm, and responding thoughtfully to the site's unique context and surrounding neighbourhood. The sites, collectively, contained 22 older and unsuitable rental units, of which 3 units (6 tenants) are currently occupied.
The revised plans change the previous L-shaped building form to a rectangular, street-facing building along Pandora Avenue. This creates a clearer building presence along the street while allowing the remainder of the site to be more effectively organized around the heritage house, outdoor amenity spaces, landscaping and neighbouring properties. Building massing is stepped back at the sixth level, with additional setbacks and architectural relief incorporated throughout the elevations. The revised building alignment also increases the rear yard setbacks and separation from neighbouring homes. Together, these measures reduce the overall mass of the building, provide greater articulation when viewed from surrounding streets and neighbouring properties, reduce overlook, and help maintain the privacy of adjacent residents. The increased setbacks also better align with the objectives of the “perimeter block” design guideline, provide greater opportunities for tree retention, and reduce the extent of excavation required on the site.
Rationale for now longer retaining the sequoia tree:
While the previous application sought to retain the existing healthy Sequoia tree, the current proposal can no longer accommodate its retention due to a combination of site constraints that emerged through the design and approval process.
As part of the redesign, the project team initially explored retaining the tree by maintaining the previous L-shaped building configuration. However, the arborist concluded that the associated root and crown loss would be significant enough that the tree should not be considered a viable retention candidate. The team also explored whether the existing BC Hydro pole and associated overhead high-voltage power lines could be relocated to reduce impacts on the tree, but discussions with BC Hydro confirmed that relocation is not feasible. Combined with BC Hydro's required 5.0 m setback from the overhead power lines and the recently adopted Engineering Bylaw requirement for a 2.6 m road dedication along the Pandora Avenue frontage, the building must be set further back into the site, resulting in encroachment into the Sequoia's critical root zone. As a result, retention of the tree is no longer feasible.